From the
organisers of
Hillhead logo

Harris decision imminent

AT last month's Court of Session in Edinburgh, Lord Hardie issued a written determination that the Scottish Executive must reach a decision within 21 days on Lafarge Redland Aggregates' application to develop a coastal quarry at Lingerabay, on the Isle of Harris.

Earlier this year the company were granted a judicial review under Lord Hardie in an effort to compel the Scottish Executive to reach a decision based on the recommendations of the report of the nine-month Public Inquiry into their application.

In September it was revealed to the Court that the report recommends that planning permission for the quarry 'should' be granted.

 

 

 

Latest Jobs

Civil Engineer (Quarries)

Forestry and Land Scotland (FLS) is seeking a Civil Engineer (Quarries) for their South Region, to manage the quarries and stone production programme