From the
organisers of
Hillhead logo

Hanson meet high-speed challenge

HANSON UK have supplied specialist concrete for the high-speed construction of the service towers for Glasgow’s new National Indoor Sports Arena and the Sir Chris Hoy Velodrome.

The £92 million venue will be one of the centrepieces of the 2014 Commonwealth Games and will then regularly host international sporting events.

Hanson supplied contractor PC Harrington with 600 cubic metres of concrete over two months for the slip-form construction of the service towers.

‘The slip-form process is less dependant on cranes, which is a benefit on a congested site,’ said Hanson UK technical manager Colin Reid. ‘It also allows the contractor to get the vertical elements of the project completed quickly, reducing construction time and costs.

‘The concrete had to set quickly so that it was self-supporting once the shutter had been moved. This allowed construction to proceed at high speed. It was a challenge to find the correct blend of admixtures and cement for the mix design, and to ensure that every truck load was the correct consistency.’

Steve Duncan, project manager with PC Harrington, added: ‘The slip-forming work for the towers was complex and we needed a supplier we could rely on to deliver a high-quality, consistent mix that would meet our target of pouring between 3.5 and 4 cubic metres of concrete each day.

‘After an initial settling in period, a daily height of 4.5m of concrete was regularly achieved, allowing production days to be reduced and delivering real cost and efficiency benefits.’

The concrete was supplied from Hanson’s Shawfield plant at Rutherglen, just two miles from the site, and was part of a total contract to supply 18,000 cubic metres over 12 months.

 
 

Latest Jobs

Civil Engineer (Quarries)

Forestry and Land Scotland (FLS) is seeking a Civil Engineer (Quarries) for their South Region, to manage the quarries and stone production programme